Structural Repair · Pinehurst · 2023

Framing Two Dormers Into the Roof of a 1983 Pinehurst Ranch

The attic over this 1983 Pinehurst ranch had the floor area for two bedrooms and none of the headroom or daylight. The roof came down to the floor on both sides, and the only light was a bulb. To make rooms up there, the roof had to open. This is the framing part of the attic remodel, which is one piece of the whole-home remodel.

We cut two openings in the front roof, one on each side of the front door, and framed a dormer in each. Each one is built from the attic floor up: walls on both sides, a header across the opening, and its own small hip roof tied back into the main roof and shingled to match. From the street they line up over the windows below, so they read as part of the house and not as something added to it.

With the dormers framed and sheathed, the attic floor was framed and the rooms were laid out under the roof. The openings did one more job before the windows went in. There was no way to carry a sheet of drywall up the stair, so every sheet for the attic went up on a telehandler and in through a dormer.

Town
Pinehurst
Completed
2023
Category
Structural & Repair
Details
Two dormers on the front roof, either side of the front door · Hip-roofed dormers, shingled to match the house · Framed from the attic floor up, with a header across each opening · Drywall delivered through the dormer openings by telehandler
The finished project
The attic as we found it: open rafters, ductwork, insulation and a plywood walkway
Then Now

BeforeThe attic as we found it: open rafters, ductwork, insulation and a plywood walkway.

AfterA finished attic bedroom, lit by its dormer.

The build

Start to finish

The attic as we found it: open rafters, ductwork, insulation and a plywood walkway
The attic as we found it: open rafters, ductwork, insulation and a plywood walkway.
New framing in the roof where the first dormer goes
New framing in the roof where the first dormer goes.
Framing the two dormers from the roof, one on each side of the front door
Framing the two dormers from the roof, one on each side of the front door.
Both dormers framed up, with the first sheathing panels on
Both dormers framed up, with the first sheathing panels on.

After

The rooms the dormers made

A finished attic bedroom, lit by its dormer
A finished attic bedroom, lit by its dormer.
The second bedroom: the roof slope, a dormer window, and a door cut to fit under the roof
The second bedroom: the roof slope, a dormer window, and a door cut to fit under the roof.
The length of the room, to the dormer window
The length of the room, to the dormer window.

Scope

The work

Opening the roof. Two openings cut in the front roof slope, with the crew framing from ladders and the roof itself.

Framed from the floor up. Each dormer has framed side walls, a header across the opening and a hip roof tied into the main roof.

Sheathed and dried in. The dormer walls were sheathed and the seams taped, and the dormer roofs were shingled to match the house.

Rooms laid out. With daylight in the attic, the floor was framed and the bedroom, bath and closet walls went up under the roof.

The way in for drywall. Sheets were lifted to the dormer openings by telehandler before the windows were set.

How we got it approved

Client hired us to do pre-construction and design. Once the plan was approved by the client, we applied for permits as required and commenced with work.