Structural Repair · Pinehurst · 2023
Framing Two Dormers Into the Roof of a 1983 Pinehurst Ranch
The attic over this 1983 Pinehurst ranch had the floor area for two bedrooms and none of the headroom or daylight. The roof came down to the floor on both sides, and the only light was a bulb. To make rooms up there, the roof had to open. This is the framing part of the attic remodel, which is one piece of the whole-home remodel.
We cut two openings in the front roof, one on each side of the front door, and framed a dormer in each. Each one is built from the attic floor up: walls on both sides, a header across the opening, and its own small hip roof tied back into the main roof and shingled to match. From the street they line up over the windows below, so they read as part of the house and not as something added to it.
With the dormers framed and sheathed, the attic floor was framed and the rooms were laid out under the roof. The openings did one more job before the windows went in. There was no way to carry a sheet of drywall up the stair, so every sheet for the attic went up on a telehandler and in through a dormer.
- Town
- Pinehurst
- Completed
- 2023
- Category
- Structural & Repair
- Details
- Two dormers on the front roof, either side of the front door · Hip-roofed dormers, shingled to match the house · Framed from the attic floor up, with a header across each opening · Drywall delivered through the dormer openings by telehandler


BeforeThe attic as we found it: open rafters, ductwork, insulation and a plywood walkway.
AfterA finished attic bedroom, lit by its dormer.
The build
Start to finish




The rest of the build







After
The rooms the dormers made



Scope
The work
Opening the roof. Two openings cut in the front roof slope, with the crew framing from ladders and the roof itself.
Framed from the floor up. Each dormer has framed side walls, a header across the opening and a hip roof tied into the main roof.
Sheathed and dried in. The dormer walls were sheathed and the seams taped, and the dormer roofs were shingled to match the house.
Rooms laid out. With daylight in the attic, the floor was framed and the bedroom, bath and closet walls went up under the roof.
The way in for drywall. Sheets were lifted to the dormer openings by telehandler before the windows were set.
How we got it approved
Client hired us to do pre-construction and design. Once the plan was approved by the client, we applied for permits as required and commenced with work.